2,000 Acuvim L Meters with AcuCT Hinged CTs & Rogowski Coil CTs — Without Replacing Existing CTs & PTs
Executive Summary
2,000 Meters | Low Downtime | Existing CT/PT Infrastructure Retained | DCS & RTU Integration
A major refinery co-generation power plant required a large-scale upgrade of its electrical power quality and energy metering infrastructure.
The key challenge was to modernize 2,000 metering points while minimizing plant downtime and shutdown intervention.
Instead of replacing the existing CTs and PTs throughout the plant, ELDAC Process Automation implemented a retrofit-based metering architecture using:
- AcuCT Hinged Split-Core CTs
- Rogowski Coil CTs
- Acuvim L multifunction power and energy meters
- Existing PTs
- AXM-WEB2-D communication modules
- Modbus RTU
- Modbus TCP/IP
- IEC 61850
- Yokogawa DCS
- Siemens S800 Series Substation RTUs
The project successfully deployed 2,000 Acuvim L meters, with:
800 meters connected to Yokogawa DCS for centralized monitoring and energy data logging.
1,200 meters connected to Siemens S800 Series Substation RTUs for the load-shedding project.
Table of Contents
1. Project Overview
| Parameter | Details |
| Industry | Refinery / Co-Generation |
| Application | Power Quality, Energy Monitoring & Load Shedding |
| Total Meters | 2,000 Acuvim L |
| Current Measurement | AcuCT Hinged CTs + Rogowski Coil CTs |
| Existing CTs | Retained where suitable |
| Existing PTs | Retained |
| Existing CT Secondary | 1 A / 5 A |
| AcuCT Output | 333 mV AC |
| PT Secondary | 110 V AC |
| Feeder Voltage Scaling | 6.6 kV / 33 kV / 66 kV |
| Yokogawa DCS | 800 Meters |
| Siemens S800 RTU | 1,200 Meters |
| Communication | RS485 Modbus RTU / Modbus TCP/IP / IEC 61850 |
| Primary Application | Monitoring, Energy Logging & Load Shedding |
| Solution Provider | ELDAC Process Automation |
2. The Customer Challenge
Modernize Metering Without a Major Shutdown
The refinery co-generation plant had an extensive existing electrical infrastructure with installed CTs, PTs, switchgear and automation systems.
Replacing the existing CTs across thousands of metering points would have required significant:
- Electrical shutdowns
- Isolation and safety procedures
- CT replacement
- Secondary wiring modifications
- Panel modifications
- Testing and commissioning
- DCS engineering
- RTU engineering
With 2,000 measurement points, even small modifications at each feeder could significantly increase installation time and shutdown requirements.
The project therefore required a solution that could:
- Modernize the metering infrastructure
- Minimize shutdown and downtime
- Retain existing CTs and PTs wherever suitable
- Avoid unnecessary rewiring
- Support different existing feeder configurations
- Integrate with existing Yokogawa DCS
- Integrate with Siemens S800 Series Substation RTUs
- Support load-shedding applications
3. The Retrofit Strategy
Retain. Retrofit. Integrate.
The project adopted a feeder-wise approach rather than a complete CT replacement strategy.
Existing CT Performing Properly
AcuCT Hinged CT
Existing CT Not Performing Properly
Rogowski Coil CT
Existing Voltage Measurement
Existing PT
Digital Metering
Acuvim L
This approach allowed the solution to adapt to the actual condition of each feeder.
4. AcuCT Hinged CT Retrofit
For feeders where the existing CT was performing properly, the existing CT was retained.
The existing CT secondary was either:
1 A or 5 A
AcuCT Hinged CTs were installed around the existing CT secondary conduct
1 A Secondary
Existing CT → 1 A
↓
AcuCT Hinged CT → 1 A / 333 mV AC
↓
Acuvim L → 333 mV AC
5 A Secondary
Existing CT → 5 A
↓
AcuCT Hinged CT → 5 A / 333 mV AC
↓
Acuvim L → 333 mV AC
5. Low-Downtime Installation Without Removing Existing CT Secondary Wires
The hinged split-core design was particularly valuable for the retrofit application.
The AcuCT could be opened and installed around the existing CT secondary conductor without removing the existing wire from the installed CT arrangement.
This reduced the requirement for:
- Secondary wiring modification
- Cable disconnection
- Extensive panel rewiring
- Long shutdown activities
Retrofit Advantage
- Install the current measurement device around the existing conductor instead of rebuilding the existing CT installation.
This was a key element of the project’s low-downtime philosophy.
6. Measuring the Actual HT Feeder Primary Current
The AcuCT provides a 333 mV AC signal to the Acuvim L.
The meter was then configured with the primary ratio of the existing HT feeder CT.
Therefore, the Acuvim L could calculate and display the corresponding primary feeder current.
Measurement Chain
HT Feeder
↓
Existing CT
↓
1 A / 5 A Secondary
↓
AcuCT Hinged CT
↓
333 mV AC
↓
Acuvim L
↓
Existing CT Primary Ratio Configured in Meter
↓
Actual HT Feeder Primary Current
This enabled the plant to use a standardized 333 mV meter input while maintaining feeder-wise primary current measurement.
7. Rogowski Coil Solution for Problematic CT Locations
Not all existing CTs were suitable for reuse.
At selected locations, existing CTs were not performing properly or were not suitable for the required measurement performance.
For these feeders, the project used Rogowski Coil CTs.
The required busbar access/modification was carried out, and the flexible Rogowski coil was installed around the busbar.
The Acuvim L was configured for Rogowski current measurement.
Measurement Chain
HT Busbar
↓
Rogowski Coil CT
↓
Acuvim L
↓
Feeder Current Measurement
This provided an alternative solution for difficult measurement locations without requiring the entire project to adopt conventional CT replacement.
8. One Meter — Multiple Current Measurement Options
A major advantage of the Acuvim L platform was the ability to accommodate different current measurement technologies.
Suitable Existing CT
Existing CT → AcuCT Hinged CT → 333 mV → Acuvim L
Problematic Existing CT
Busbar → Rogowski Coil → Acuvim L
This created a flexible feeder-by-feeder retrofit strategy.
Instead of forcing one CT technology across the entire plant, the appropriate solution could be selected
according to the existing electrical condition.
9. Existing PTs Retained
The existing PT infrastructure was also retained.
The existing PT secondary provided:
110 V AC
This signal was connected to the Acuvim L.
The meters were configured feeder-wise for the applicable primary voltage.
Voltage Levels Included
- 6.6 kV
- 33 kV
- 66 kV
Voltage Measurement
Existing PT
↓
110 V AC
↓
Acuvim L
↓
Feeder-Wise PT Ratio Scaling
↓
6.6 / 33 / 66 kV Primary Voltage
This eliminated the need for unnecessary PT replacement as part of the metering modernization.
10. 1,200 Meters — Siemens S800 Series Substation RTUs
A total of:
1,200 Acuvim L Meters
were equipped with AXM-WEB2-D add-on communication cards.
The communication architecture used:
Modbus TCP/IP
and
IEC 61850
The meters were integrated with Siemens S800 Series Substation RTUs for the plant’s load-shedding project.
Communication Architecture
1,200 Acuvim L
↓
AXM-WEB2-D
↓
Modbus TCP/IP / IEC 61850
↓
Siemens S800 Series Substation RTUs
↓
Load Shedding
This transformed the meters from standalone measurement devices into an integral part of the
substation automation architecture.
11. 800 Meters — Yokogawa DCS Integration
A further:
800 Acuvim L Meters
were integrated with the Yokogawa DCS.
The meters used their onboard:
RS485 Modbus RTU
communication.
The meters were connected in a daisy-chain RS485 network.
Communication Architecture
800 Acuvim L Meters
↓
RS485 Daisy Chain
↓
Modbus RTU
↓
Yokogawa DCS
↓
Centralized Monitoring & Energy Data Logging
12. Energy Import & Export Monitoring
The Yokogawa DCS network enabled centralized monitoring and logging of electrical energy data.
Key monitored parameters included:
- Energy Import
- Energy Export
- Voltage
- Current
- Active Power
- Reactive Power
- Apparent Power
- Power Factor
- Energy Data
This enabled the plant to bring electrical information from hundreds of field measurement points into
the centralized DCS environment.
13. Load-Shedding Application
The 1,200-meter Siemens S800 RTU network formed part of the plant’s load-shedding project.
Architecture
Feeder
↓
Acuvim L
↓
AXM-WEB2-D
↓
Modbus TCP/IP / IEC 61850
↓
Siemens S800 Series Substation RTU
↓
Load-Shedding System
This demonstrates that the metering system was integrated not only for monitoring, but also into the plant’s broader electrical automation architecture.
14. Complete System Architecture
Current Measurement
Existing CT Performing Properly
→ AcuCT Hinged CT
Existing CT Not Performing Properly
→ Rogowski Coil CT
Voltage Measurement
Existing PT
→ 110 V AC
Digital Metering
2,000 Acuvim L Meters
↓
Automation Integration
1,200 Meters
AXM-WEB2-D
→ Modbus TCP/IP / IEC 61850
→ Siemens S800 Series Substation RTUs
→ Load Shedding
800 Meters
RS485 Modbus RTU
→ Yokogawa DCS
→ Monitoring & Energy Data Logging
15. Project Results
The retrofit delivered a large-scale connected electrical monitoring system while preserving a significant
portion of the existing electrical infrastructure.
2,000
Acuvim L meters installed
1,200
Meters integrated with Siemens S800 Series RTUs
800
Meters integrated with Yokogawa DCS
2 CT Technologies
AcuCT Hinged + Rogowski Coil
3 HT Voltage Levels
6.6 kV + 33 kV + 66 kV
3 Industrial Communication Methods
Modbus RTU + Modbus TCP/IP + IEC 61850
16. Key Benefits
Low-Downtime Retrofit
Reduced the need for extensive electrical modifications and shutdown intervention.
Existing CTs Retained
Suitable existing CTs remained in service.
No Need to Remove Existing CT Secondary Wires
Hinged CT installation simplified retrofit current measurement.
Rogowski Solution for Difficult Locations
Provided an alternative where existing CT performance was inadequate.
Existing PTs Retained
Existing 110 V AC PT secondary signals were used.
Actual Primary Current Measurement
Existing CT primary ratios were configured in the Acuvim L.
Large-Scale DCS Integration
800 meters connected through RS485 Modbus RTU.
Substation Automation Integration
1,200 meters connected through AXM-WEB2-D using Modbus TCP/IP and IEC 61850.
Load-Shedding Application
Metering data integrated into the Siemens S800 Series Substation RTU architecture.
Energy Import & Export Monitoring
Centralized monitoring and logging through the Yokogawa DCS.
17. Why This Case Study Matters
This project demonstrates that a large industrial metering upgrade does not necessarily require a complete replacement of the existing electrical infrastructure.
A carefully engineered retrofit can combine:
Existing CTs
+
AcuCT Hinged CTs
+
Rogowski Coil CTs
+
Existing PTs
+
Acuvim L
+
Modbus RTU
+
Modbus TCP/IP
+
IEC 61850
+
Yokogawa DCS
+
Siemens S800 Series Substation RTUs
to create a modern connected electrical monitoring and automation system.
18. ELDAC Process Automation — Retrofit Engineering Expertise
The success of this project demonstrates ELDAC Process Automation’s capability to engineer large-scale power quality, energy monitoring and electrical automation retrofit solutions around existing plant infrastructure.
Rather than simply replacing meters, the solution considered the complete system:
Existing Electrical Infrastructure → Current Measurement → Voltage Measurement → Power
Metering → Communication → DCS / RTU → Application
The result was a 2,000-point electrical measurement network designed around the plant’s existing
CTs, PTs, feeder configurations and automation systems.
The Takeaway
2,000 Meters. Low Downtime. Existing CTs & PTs Retained. Two Automation Platforms. Multiple CT Technologies.
This refinery co-generation project demonstrates a practical path for industries looking to modernize
their electrical metering infrastructure without turning every metering upgrade into a major
shutdown project.